Minutes from ISOLDE Physics Group meeting, 24th August 2016.
No comments to the minutes from the previous PG meeting:
Please read the minutes.
Technical news:
- Overall it has again been a good week at ISOLDE.
ISOLDE:
- ISOLDE:
- The tape station is not behaving correctly.
- This will be investigated ASAP by G. Jan Focker
- A “burning smell” was noticed in the hall.
- It turned out to be a bad belt in the ventilation system. The belt was replaced.
- The tape station is not behaving correctly.
- HRS:
- Delivered Ra beam to CRIS from Wednesday.
- The Mag90 went into fault 2 times in 3h
- A power cycle of the controller cured the issue.
- The run continued until the target delivered a leak Tuesday morning.
- This can be expected from an old target that has been used for about 2 weeks in all and which had taken 6e18 protons.
- GPS:
- Delivered Beam for ISOLTRAP until Wednesday
- Setting up the Hg beam
- The extraction electrode again went into position 64 without setting it to this value (some default position).
- This has now happened 2-3 times, the reason is still unclear but it seems to be related to the controls.
- The VISTAR information on the Mag70 is in error – to be fixed ASAP.
- A new software update was installed.
- It does not display the mass value.
- But when Green all is fine. Only Red is a real error.
- It was problematic to tune the beam at 30 keV to LA1.
- A retuning of the separator at 50 keV was performed and this gave better transmission.
- RILIS:
- Had a good Ra-run for CRIS.
- Now setting up for Bi-run.
- Together with ISOLTRAP and COLLAPS they want to further investigate a strange isomer state of Bi, that may have been observed during the windmill/ISOLTRAP run this year.
- Plan to install new shutters (similar to installed at AWAKE) for laser blocking during the shutdown period.
- REX/HIE:
- Pulses are now stretched to 1 ms.
- There were problems with the 7-gap III amplifier which was limited to an A/q of 4.0. To go beyond this to A/q = 4.3 (for 2016 physics) a bigger intervention than expected was required and this resulted in a day of downtime.
- A Si-detector (after the first cryo-module) had to be replaced.
- Beam is now through the 4th Cryo-module at 3.9 MeV/u.
- Although the cryo-temperature controllers are working ok – work is needed to make the control perform more stable. With each new cryo-module turned on the system becomes unstable. Discussions are ongoing about stabilising the system.
- Targets:
- The production of first targets for the HIE-run is on time. Nano-UCx (prototype) #581 target was not installed as it was a bad target, due to issues with a new polymer material that turned out to be very reactive.
- The new polymer was used to speed up production time.
- This is to be investigated.
- Used targets will be installed on both HRS and GPS for the next beam time.
- The production of first targets for the HIE-run is on time. Nano-UCx (prototype) #581 target was not installed as it was a bad target, due to issues with a new polymer material that turned out to be very reactive.
Physics:
- CRIS:
- They studied the hyperfine structures of neutron-rich Radium isotopes, 222- to 234-Ra.
- Overall a good run and they are happy.
- The 2-3 days of extra run was well used.
- They changed between low resolution and high resolution scans to map out the hyperfine levels.
- LA1:
- A traveling setup, TATRA, will take 188Hg-beams from GPS.
- They want to measure conversion electrons.
- For this purpose they have window-less detectors and need a high vacuum.
- The vacuum perform well also with open to ISOLDE target.
- GLM:
- On standby is Mossbauer for biophysics using 197Hg decaying to 197Au.
- Study the binding of Hg in molecules.
- Want a few collections for feasibility test, as this study has never been done before.
- On standby is Mossbauer for biophysics using 197Hg decaying to 197Au.
Safety:
- Target:
- Due to the bad nano-UCx target produced last week (the reactive polymer), the safety issues regarding the handling and procedure for nano material will be reviewed.
- The production of nano-targets are on hold.
- This pause will have no effect on the remaining beam times for this year.
- Due to the bad nano-UCx target produced last week (the reactive polymer), the safety issues regarding the handling and procedure for nano material will be reviewed.
- ISOLDE:
- The access to ISOLDE should no longer have a delay (3 min) on the “2nd access”.
- TSO:
- Magda is the new TSO of b275, replacing Maria who becomes the DTSO.
AOB:
- EDH:
- The CERN EDH system will change 31 August (likely a few days earlier).
- Please plan ahead your orders for instance LN2, as moving to the new system could result in system errors.
- The CERN EDH system will change 31 August (likely a few days earlier).
- LN2 delivery:
- Please do not remove the adaptor on the empty dewar for refilling.
- 508 workshop:
- A power adaptor (German to Swiss) for the vacuum cleaner has been ordered.
- Summer students:
- The summer students presentations were:
- Thomas Guldager Skov: A Plasma Ion Source for ISOLTRA
- Ingrid Strandberg: Linewidth simulations & offline ion source for MIRACLS
- The summer students presentations were:
The next ISOLDE PG meeting will be held on 31 August 2016 followed by two summer student presentations from: Kritsana and Kris Gavana
Minutes taken by ~TEM