8 October 2014

Minutes from the ISOLDE Physics Group meeting on October 8, 2014

No comments on the minutes for the meetings of October 1st .

Technical news

GPS

  • Ta target for 11Li production at LA1. A few issues with protons during the run, watchdog, LINAC 2 and magnets in the BTY line. All problems fixed by Saturday night.
  • The separator magnet “hysteresis” problem (i.e. the beam was a few mm off when coming from low or high mass) was not observed by the technical or RILIS teams with this target.
    • The engineer in charge reports that large steering was required to center the beam and obtain good transmission after the separator. Tim Giles will follow up the problem.
    • Transmission problems have been observed in many GPS targets so far. This point to a possible alignment problem. Users are reminded to keep it in mind when tuning GPS beams.
  • There were 2 HV trips at the beginning of the IS525 run. It’s been running stably at 50 kV since.
    • Technical team noticed that sometimes after rebooting the HV pulsing mode does not start at first try and HV goes to static mode – this worsens the HV recovery and can break the HV installation.
    •  It is recommended to make sure pulsing mode is engaged to protect the HV platform.
  • Scanner SC482 does not work. If all needed parts become available; it will be replaced next Monday.
  • RILIS laser position had shifted on Wednesday morning, causing beam 11Li intensity fluctuations. Beam intensity recovered  previous values after RILIS team corrected the shift (50% higher with laser on than off).
  • Target change postponed to Monday after the HRS intervention planned for Friday. GLM/GHM collections on Thursday; IS525 extended to run through the weekend.

HRS

  • After uncoupling the problematic piston from the target table/platform both the table and the piston moved freely again. This suggests that the rigid coupling of the piston was indeed the problem.
  • A new commercial piston has been received. It contains plastic parts, which are not radiation resistant.
    • The all-metallic design will not be used again. The coating degraded due to friction in regular operations.
    • As in previous years the commercial pistons will now be removed at the end of the year, every year.
    • The piston will be fitted with a spherical tip to ensure it can be realigned.
    • The intervention to install all parts mentioned is planned for this Friday (update after PG meeting: intervention now planned for Monday 13th of October).
  • CRIS experiment, requiring HRS, will be hopefully scheduled once HRS is fixed.

RILIS                                                  

  • The parts required to repair the pumps of the two TiSa lasers will be delivered in 1 month.
  • The spare pump laser is currently in use for IS525.

 

REX-ISOLDE

  • Twin-EBIS current increased to 500 mA compared to previous 200 mA at REX-EBIS. This will allow for faster and higher charge breeding at REX, but at the expense of a reduced cathode life.

 

Miscellanea

  • The HRS schedule for the remainder of the year will be released after the status of the piston repair is evaluated post intervention.
  • A new pair of cryogenics safety gloves were purchased and are now at the ISOLDE toolbox.

IS525 at LA1

  • The IS525 experiment will measure the energy of neutrons emitted in the beta decay of 11Li, both single and double neutron emission.
  • As of Wednesday, 10 shifts of 11Li at 1000 cps or higher beta-rate; 3 hours of 9Li with 8 ms beam gate (20 000 cps beta-rate) to measure the beta-decay half-life.
  • Collected 10 times more statistics than the previous experiment by Hirayama and collaborators.
  • 500 two-neutron coincidences observed in the 3 shifts analyzed, after cross-talk filter applied. This corresponds to 50% of the experiment goal in 1/5 of the allotted time.

 

  • COLLAPS laser was mounted in the CRIS laser table in the hall and it is working stable.

IDS

  • IDS electrical and LN2 safety checks have been approved and signed by safety department
  • The setup is being prepared for 31Ar run; Clover frame was turned around; IEM-CSIC chamber and silicon detectors installed;

 

The next meeting will take place at the same time Thursday next week (2pm, 16th October 2014) and it will be followed by the seminar of Claes Fahlander on Superheavy research.

Minutes taken by MMF