14 January 2009

  1. Technical News (Offline work)
  • Cranes are being tested.
  • Implementation of fast tape station controls is ongoing
  • Implementation of ISCOOL vacuum controls is ongoing
  • Pressurized air tubes are being repaired throughout the ISOLDE hall
  • COLLAPS, (future) CRIS, ISOLTRAP and Solid State Lab : Forms are to be completed on risk assessment and safety issues for operation of the lasers
  • A laser safety interlock is to be implemented at the RILIS laser cabin
  • FC’s and scanners are being repaired in the next weeks
  1. AOB
  • Welcome to our guest students from Slovakia : Rastislav Dwornicky  (working at ISOLTRAP) and Rastislav Hodak (working for the target group)
  • Summer student projects : deadline for submission 12/02/2009. Please send project description to Yorick and Alex first.
  • Talk by Rasto on theoretical work he’s done on double beta decay.

 

Minutes by Jarno