Category: Physics Group Meeting Minutes

  • 27 January 2010

    27 January 2010 Minutes by DTY Date 2010-01-27

    Explore →

  • 20 January 2010

    20 January 2010 1. Technical news: · The targets from 2009 have been removed and stored in the ISR · The front-end exchange is progressing as scheduled · Current activities: – Change of the Boris tube – Maintenance of turbo pumps and vacuum-gauges replacement – Improving the vacuum for the REX injection line · Planned

    Explore →

  • 7 December 2009

    7 December 2009 The other fellowship was turned down as apparently another vacancy became more attracting. Therefore, ISOLDE could get another fellow in the next call. Date 2009-12-07

    Explore →

  • 25 November 2009

    25 November 2009 Minutes by DTY Date 2009-11-25

    Explore →

  • 21 October 2009

    21 October 2009 Minutes by Jarno Date 2009-10-21

    Explore →

  • 14 October 2009

    14 October 2009 – Week 49 : stop of both Front Ends (FE’s) – Week 47 : start work on vacuum system (beamlines only available up to CA0) – 07/12 : cooling water stop – 27/02 : cooling water back – 01/2010 – 04/2010 : installation new HRS frontend (FE#6) – Startup of ISOLDE end

    Explore →

  • 7 October 2009

    7 October 2009 Minutes by Jarno Date 2009-10-07

    Explore →

  • 29 September 2009

    29 September 2009 Minutes by Jarno Date 2009-09-29

    Explore →

  • 27 August 2009

    27 August 2009 Minutes by Jarno Date 2009-08-27

    Explore →

  • 19 August 2009

    19 August 2009 Minutes by Jarno Date 2009-08-19

    Explore →