31 August 2016

Minutes from ISOLDE Physics Group meeting, 31st August 2016.

No comments to the minutes from the previous PG meeting: 

Please read the minutes.

Technical news:

  • A Technical STOP on LINAC2 is planned for Wednesday/Thursday (in week 37) in order to exchange the degrading cathode. 

ISOLDE:     

  • Comments from the ISOLDE operators: USERS at ISOLDE should know the basic ISOLDE operations and at least one USER should have taken the ISOLDE Separator course. Especially when experiments are running at night.
  • Due to the problems with the HRS targets change, there was some re-scheduling of beam times this week. The collections on the GPS were cancelled and the Bi run was extended into the weekend as LOI168 are not yet ready.

 

  • HRS:
    • Was on stand-by until Thursday.
    • There were issues during target change Thursday/Friday.
      • Problems with unclamping the target
      • The installed old target (#573) showed a leak.
        • Another target (#562) was installed to exclude front-end leak. The front-end is in good shape, but more tests will be performed later this year.
    • Target #574 has now been installed for Bi-run.
      • Pump-down and heating took longer than expected (outgassing), but the target is not leaking.

 

 

  • GPS:
    • Has a reused lead target installed for Hg-beams #577. 3rd time this year that this target has been used!
      • Delivered Hg-beams to mainly LA1 and only to GLM when LA1 was not taking beam.
    • The beam setup was not easy, due to a double peak/wide peak from the target and ion source which is obviously not optimal
    • Difficult beam tuning to LA1. A good beam could finally be delivered to the experiment on Friday afternoon.
    • Beam tuning to the GLM was easier as the profile of the beam was less of an issue.
    • Again during beam setup the extraction electrode moved into position 64 by itself.
      • The reason for this issue is still unknown and is being investigated. Maybe it is some default value in the software that overwrites.
    • Problems with the tape station during beam setup – tape full error.
      • Gerrit Jan investigated and found that the PLC had stopped working. The PLC was replaced and tape station is up running again.
      • The new tape station should be taken into operation ASAP, since the old tape station is in bad/old condition.
    • The line dropped to 0A on Saturday and both target and line on Sunday.
    • For the second failure on Sunday, the main circuit breaker went off – maybe due to spark protection.
      • This is being investigated by experts.

 

  • RILIS:
    • Has been setting up for Bi-beams.
    • Bi is currently running on HRS
    • Next they will switch to Sn isotopes for HIE-run.

 

 

  • REX/HIE:
    • The control of the cryo-modules has become more stable.
    • For the coming HIE-run the energy is at 5.35 MeV/u (the aim was 5.5 MeV/u).
      • They now concentrate on getting beam transmission and not a higher beam energy.
    • A simpler interface panel for the superconducting cavities has been introduced.
      • It is still under discussion if USERS should have access to e.g. reset tripped cavities.
      • In any case USER training will be needed for experiments with HIE.

 

  • Targets:
    • The production is going well and on track.
    • LaC target for HIE-run is soon done and will be online on Friday.

Physics:

 

  • LA1:      
    • The traveling setup, TATRA, was taking 189Hg and 183Hg-beams from GPS.
    • They wanted to measure conversion electrons to complete the previous gama-gama study.
    • Unfortunately when they finally had good beam transmission their tape broke two times. This could be fast repaired during beam time, and had to wait (2-3 h) for high vacuum.
      • However, they got good/enough data for proof of principle.
      • The run was to demonstrate that they could measure conversion electrons with a very high resolution and this was shown. They will come back to the INTC with an addendum.

 

  • GLM:
    • Measured emission Mossbauer spectroscopy for biophysics using 197Hg decaying to 197Au.
    • Got some collections done when LA1 was not taking beam.
      • Was difficult to collect enough activity in the ice.
      • A spectrum was obtained.
      • Was an overall ok beam-time that proved feasibility of the isotope and the setup.

 

  • Bi-run on HRS
    • This week RILIS, ISOLTRAP, and COLLAPS want to further investigate a strange isomer state of Bi, that may have been observed during the windmill/ISOLTRAP run this year.

 

  • HIE
    • Next week HIE-run is planned to start with 110- and 108Sn beams.
    • Beams should be delivered before the 8th (holiday Jeune genevois).

Safety:

  • Target:
    • The production of nano-targets has been reviewed and should improve the production procedure, but for the moment, production is still on hold (this will not affect beam time this year).
    • The proton integrator on target (for GPS) was not turned ON.
      • This is important to know the target irradiation and for RP.
      • The number of protons being integrated should change with time – if not, please notify Operator.

 

 

AOB:

 

  • Summer students:
    • The summer students presentations were:
      • Kritsana Srakaew: Validation and testing of the collection chambers for the CERN-MEDICIS project.
      • Chris Gavanas: Summer Student Report, Script to automate tasks ASAP (After Set-Up Auto Save Application).

 

 

 

The next ISOLDE PG meeting will be held on 7 September 2016 followed by:

  • Summer student presentation from Christoffer Ricketts.
  • PG Seminar by Dan lascar "Recent TITAN Measurements and EMMATrap: An Introduction".

 

 

Minutes taken by ~TEM