Minutes from ISOLDE Physics Group meeting, 31st August 2016.
No comments to the minutes from the previous PG meeting:
Please read the minutes.
Technical news:
- A Technical STOP on LINAC2 is planned for Wednesday/Thursday (in week 37) in order to exchange the degrading cathode.
ISOLDE:
- Comments from the ISOLDE operators: USERS at ISOLDE should know the basic ISOLDE operations and at least one USER should have taken the ISOLDE Separator course. Especially when experiments are running at night.
- Due to the problems with the HRS targets change, there was some re-scheduling of beam times this week. The collections on the GPS were cancelled and the Bi run was extended into the weekend as LOI168 are not yet ready.
- HRS:
- Was on stand-by until Thursday.
- There were issues during target change Thursday/Friday.
- Problems with unclamping the target
- The installed old target (#573) showed a leak.
- Another target (#562) was installed to exclude front-end leak. The front-end is in good shape, but more tests will be performed later this year.
- Target #574 has now been installed for Bi-run.
- Pump-down and heating took longer than expected (outgassing), but the target is not leaking.
- GPS:
- Has a reused lead target installed for Hg-beams #577. 3rd time this year that this target has been used!
- Delivered Hg-beams to mainly LA1 and only to GLM when LA1 was not taking beam.
- The beam setup was not easy, due to a double peak/wide peak from the target and ion source which is obviously not optimal
- Difficult beam tuning to LA1. A good beam could finally be delivered to the experiment on Friday afternoon.
- Beam tuning to the GLM was easier as the profile of the beam was less of an issue.
- Again during beam setup the extraction electrode moved into position 64 by itself.
- The reason for this issue is still unknown and is being investigated. Maybe it is some default value in the software that overwrites.
- Problems with the tape station during beam setup – tape full error.
- Gerrit Jan investigated and found that the PLC had stopped working. The PLC was replaced and tape station is up running again.
- The new tape station should be taken into operation ASAP, since the old tape station is in bad/old condition.
- The line dropped to 0A on Saturday and both target and line on Sunday.
- For the second failure on Sunday, the main circuit breaker went off – maybe due to spark protection.
- This is being investigated by experts.
- Has a reused lead target installed for Hg-beams #577. 3rd time this year that this target has been used!
- RILIS:
- Has been setting up for Bi-beams.
- Bi is currently running on HRS
- Next they will switch to Sn isotopes for HIE-run.
- REX/HIE:
- The control of the cryo-modules has become more stable.
- For the coming HIE-run the energy is at 5.35 MeV/u (the aim was 5.5 MeV/u).
- They now concentrate on getting beam transmission and not a higher beam energy.
- A simpler interface panel for the superconducting cavities has been introduced.
- It is still under discussion if USERS should have access to e.g. reset tripped cavities.
- In any case USER training will be needed for experiments with HIE.
- Targets:
- The production is going well and on track.
- LaC target for HIE-run is soon done and will be online on Friday.
Physics:
- LA1:
- The traveling setup, TATRA, was taking 189Hg and 183Hg-beams from GPS.
- They wanted to measure conversion electrons to complete the previous gama-gama study.
- Unfortunately when they finally had good beam transmission their tape broke two times. This could be fast repaired during beam time, and had to wait (2-3 h) for high vacuum.
- However, they got good/enough data for proof of principle.
- The run was to demonstrate that they could measure conversion electrons with a very high resolution and this was shown. They will come back to the INTC with an addendum.
- GLM:
- Measured emission Mossbauer spectroscopy for biophysics using 197Hg decaying to 197Au.
- Got some collections done when LA1 was not taking beam.
- Was difficult to collect enough activity in the ice.
- A spectrum was obtained.
- Was an overall ok beam-time that proved feasibility of the isotope and the setup.
- Bi-run on HRS
- This week RILIS, ISOLTRAP, and COLLAPS want to further investigate a strange isomer state of Bi, that may have been observed during the windmill/ISOLTRAP run this year.
- HIE
- Next week HIE-run is planned to start with 110- and 108Sn beams.
- Beams should be delivered before the 8th (holiday Jeune genevois).
Safety:
- Target:
- The production of nano-targets has been reviewed and should improve the production procedure, but for the moment, production is still on hold (this will not affect beam time this year).
- The proton integrator on target (for GPS) was not turned ON.
- This is important to know the target irradiation and for RP.
- The number of protons being integrated should change with time – if not, please notify Operator.
AOB:
- Summer students:
- The summer students presentations were:
- Kritsana Srakaew: Validation and testing of the collection chambers for the CERN-MEDICIS project.
- Chris Gavanas: Summer Student Report, Script to automate tasks ASAP (After Set-Up Auto Save Application).
- The summer students presentations were:
The next ISOLDE PG meeting will be held on 7 September 2016 followed by:
- Summer student presentation from Christoffer Ricketts.
- PG Seminar by Dan lascar "Recent TITAN Measurements and EMMATrap: An Introduction".
Minutes taken by ~TEM